2024, Nanjing's major urban construction plan revealed!

Recently, the NJGIP 2024
Officially out! The city arranged a total of 232 government investment plan projects in four categories, with an annual planned investment of 51.552 billion yuan. From the schedule, we found a large number of railroads, river crossings, subways, hospitals, schools, etc. are among them!
Let's see if there's one you're concerned about!

1. North Yanjiang High-speed Railway (including the construction of the station building of Nanjing North Railway Station)
Starting and ending years of construction: 2022-2026
Construction content: along the existing Ninghe Railway corridor, introduced into the Nanjing North Station, along the Yangzi Ethylene special line, Ningqi Railway corridor, set up a station through Liuhe, eastward access to Yizheng, Nanjing, the total length of the line is about 63.5 kilometers.
Image progress in 2024: promote the whole line of roadbed project and other offline projects, Liuhe Special Bridge across the Changshen Highway continuous beams and cable-stayed bridge across the Chu River Special Bridge controlling node project construction, prefabricated girder construction and girder erection construction.
2、Ninghuai Intercity Railway
Starting and ending years of construction: 2022-2026
Construction content: from the vicinity of Yishan to the south, set up Liuhe West Station near Ma'an Airport, parallel with the North Yanjiang High-speed Railway, and introduce Nanjing North Station from the west to the east, with a total line length of 60.7 kilometers.
Image Progress in 2024: Promote the roadbed project and other offline projects along the whole line, construction of Liuhe West Viaduct and Liuhe Two-Lane Special Bridge controlling project nodes, prefabricated girder construction and girder erection construction.
3. South Yanjiang Intercity Railway
Construction start and end date: 2018-2023
Construction content: from the Nanjing South Station Ning'an field lead out, using the east side of the Ninghang Passenger Dedicated line position program, the main line through the existing Jiangning Station, eastward access to the Jurong Station, the total length of the line in Nanjing is about 33.8 kilometers.
2024 image progress: engineering clearance
4、Ningwu Railway Expansion and Improvement Project
Starting and ending years of construction: 2022-2027
Construction content: the new outer winding line (Cangbo Gate to Guxiong section) and Jiangning Town Yard; the new line for the electrification of the double line railroad, the total length of the line is about 29.7 kilometers; the new Jiangning Town Yard is located in the Jiangning Riverside Development Zone, occupies an area of about 1,580 acres, the design capacity of 2.4 million tons/year
Image Progress in 2024: Actively promote the land assembly and land acquisition and relocation work, and promote the construction of Nanjing South Tunnel shield starting shaft and Qinhuai River Special Bridge.
5、Shangyuanmen River Crossing
Starting and ending years of construction: 2023-2028
Construction content: lead from Nanjing North Station, along the Pusi Road in the form of a tunnel through the Yangtze River, south of the river through the water plant on the Yuanmen folded to the southeast along the planning of the channel into the Nanjing Station, the channel is 18.76 kilometers long, the design speed of 200 kilometers per hour
Image progress in 2024: Completion of the construction work on the advance sites such as the construction of the Jiangbei work shaft, Jiangnan work shaft and the construction of the inclined shaft.
6. Longtan River Crossing
Construction start date: 2019-2024
Construction content: from the Yizheng territory of the Yangtze River embankment in the north of the river, to bridge across the main channel of the Yangtze River, through the Nanjing Longtan, stopping at the intersection with the 338 Provincial Highway; the entire project according to the bidirectional six-lane highway standard construction, the design speed of 100 kilometers per hour; the route length of 4,925 meters, the main bridge using the main span of 1,560 meters of parallel cable-stayed steel box girder suspension bridges, approach bridges using a steel-hybrid combination of girder structures
2024 Image Progress: advancing the construction of the main bridge.
7. Xianxin Road Crossing Project
Starting and ending years of construction: 2018-2025
Construction content: Starting from Kechuang intersection, laying along Xianxin Road, crossing Qixia Avenue, Hengjing Road, Hengguang Road, Hengtong Avenue, Xingang Avenue in turn, grounding at Longshan Memorial Forest, crossing the Yangtze River in the form of a bridge after passing through the Wulong Mountain, and then crossing the Shugang Avenue, Chemical Industry Avenue, the North Sixth Road, the Jiangbei River Highway, and grounding the Chu River, with the length of about 13.2 kilometers.
Image progress in 2024: except for the Jiangbei Yanjiang Interchange which has not yet been approved to start construction, part of the ramp of Qixia Interchange affected by the relocation of chemical pipeline corridor and a small amount of finishing work, the rest of the project will be completed in full, and we will strive to realize the goal of opening to traffic.
8、Jianning West Road Crossing Project
Starting and ending years of construction: 2018-2025
Construction content: Starting from the Jiangbei New District of Xingpu Road and Jiangbei Expressway intersection, southward along the Xingpu Road by tunneling through the Yangtze River to the south bank, along the current Jianning Road layout, under the Jiangbian Road, Huimin Road, stopping at the intersection of Jianning Road West and the Hot River Road, a total length of about 6.8 kilometers.

Image progress in 2024: the construction of railway-related works, Jiangbei Avenue interchange structure, Hengjiang Avenue interchange structure is completed, and the construction of the main structure of Huimin Road interchange is basically completed; carry out the construction of underground works decoration, electromechanical system and road surface.
9、Nanjing Metro Line 3 Phase III Project
Start and end of construction: 2021-2025
Construction content: starting from Muozhou East Road Station, ending at Moling Street Station, line length 3.3 kilometers, set up 2 stations
Image progress in 2024: civil construction wrapped up, stations and intervals to carry out track and installation and decoration construction.
10、Nanjing Metro Line 4 Phase II Project
Construction period: 2020-2026
Construction content: Longjiang Station to Pearl Spring Station, about 10 kilometers long, with 6 underground stations.

Image 2024: civil works carried out

11. Nanjing Metro Line 5 Project

Construction start and end years: 2016-2025 construction content: starting from Fangjiaying station, ending at Jiyin Avenue station, line length 37.4 kilometers, with 30 stations 2024 image progress: civil construction wrapping up, stations, intervals to carry out the track and installation and decoration construction, of which the Jiangning section with the opening of the initial operating conditions.

12. Nanjing Metro Line 6 Project
Construction start date: 2019-2025
Construction content: Starting from Qixia Mountain North Station and ending at Nanjing South Station, the line is 32.4 kilometers long, with 19 stations.
Image progress 2024: civil works, track works and installation and decoration works carried out
13. Nanjing Metro Line 7 Project
Start and end of construction: 2017-2024
Construction content: starting from Xishanqiao Station and ending at Xianxin Road Station, with a total line length of 35.5 kilometers and 27 stations.
Image progress in 2024: civil construction is finalized, stations and intervals carry out track and installation and decoration construction, and have the conditions for opening initial operation.
14、Nanjing Metro Line 9 Phase I Project
Construction start date: 2019-2025
Construction content: Starting from Hongshan New Town Station, ending at Jiangsu Grand Theater Constitution Park Station, the line is 19.7 kilometers long, with 16 stations.
Image progress in 2024: carry out civil works, track works and installation and decoration construction.

15. Nanjing Metro Line 10 Phase II Project
Construction start date: 2019-2025
Construction content: starting from Andemen Station and ending at Dongqi Road Station, with a total line length of 13.3 kilometers and 10 stations.
Image progress 2024: civil works, track works and installation and decoration works carried out
16、Nanjing Metro Line 11 Phase I Project
Starting and ending years of construction: 2021-2026
Construction content: Puzhou Road Station to Mamule Wei Station, a total length of about 26.7 kilometers, 19 underground stations, 1 aboveground station
Image 2024: civil works carried out
17、Nanjing-Maanshan City Regional (Suburban) Railway (Nanjing Section))
Start and end of construction: 2021-2025
Construction content: starting from Xishanqiao Station and ending at Tongjing Station, with a total line length of 26.5 kilometers and 8 stations.
Image progress in 2024: carry out civil engineering construction, part of the section with conditions to transfer to the track and station installation and decoration process
18. Huimin Avenue comprehensive renovation project
Construction start date: 2019-2025
Construction content: south from Huimin Avenue and Xinxing Road intersection, north to Huimin Avenue and Fangjiaying South Road intersection, the main line tunnel is about 1.65 kilometers long, the comprehensive pipeline corridor is 1.97 kilometers long, along with the construction of the whole line of the slow-moving system.
Image progress in 2024: main tunnel envelope completed 95%; main tunnel pit earth excavation completed 70%; main tunnel main structure completed 70%; planning pipeline completed 50%.
19. Construction of the Second Airport Corridor (north of the roundabout)
Construction period: 2020-2025
Construction content: urban expressway, Xiaoxing elevated to the roundabout highway, about 1.4 kilometers long, red line width of 60 meters
2024 image progress: main construction
20、Daishan Middle Road North Extension Project
Start and end of construction: 2021-2025
Construction content: from Daishan North Road in the south to Longzang Avenue in the north, a total length of 1.64 kilometers (of which Daishan North Road to Tianbaoqiao Road 260 meters for the transformation of the old road), the standard width of 40-45 meters
2024 image progress: main construction
21. Nanjing Children's Hospital Hexi Hospital District Phase II Project
Starting and ending years of construction: 2023-2027
Construction content: total construction area of about 137,249 square meters, the construction of basic rooms, medical equipment rooms, research rooms, teaching rooms, training rooms and underground parking facilities, etc.

2024 image progress: deep foundation horizontal support construction, foundation earth excavation and transportation.
22. Construction Project of Dingjiazhuang Hospital District, Nanjing Maternal and Child Healthcare Hospital
Construction start date: 2019-2024
Construction content: Dingjiazhuang Hospital District project consists of three plots, A, B and C, with a total number of 1,200 beds and a total construction area of 293,000 square meters, including the emergency department, outpatient department, inpatient department, medical technology department, hospital life, scientific research rooms, teaching rooms, administrative rooms, underground parking, underground security systems, wartime hospitals, and ancillary services and facilities.
23. Xuanwu District Cherry Sea Apartments and other 15 old neighborhoods renovation project
Start and end date of construction: 2024
Construction content: remediation of building roofs, external facades and internal building paths, sequencing of weak electricity, dredging of pipe networks in the area, road disease treatment, and improvement of greening, street lighting, parking, security and other ancillary facilities.
24. Qinhuai District, Li Fu Street No. 4 and other 16 old neighborhood renovation projects
Start and end date of construction: 2024
Construction content: housing renovation, road renovation, adding street lights, non-motorized shed renovation, landscape green replanting, weak electricity pipeline renovation, and improvement of basic supporting facilities.
25. Renovation of 10 old neighborhoods, including Huxi Village in Jianye District
Start and end date of construction: 2024
Construction content: 10 neighborhoods in Jianye District, including Huxi Village and Feng Ya Yuan, with new facades, roof waterproofing repairs (replacement), new internal hallways, road reconstruction, greening, additional parking lots, and repair (replacement) of unit doors.
26. Rehabilitation projects for 26 old districts, including Emei Ling No. 19 District, Gulou District
Start and end date of construction: 2024
Construction content: a total of 26 neighborhoods, the main implementation of the house facade roof new, greening, road reconstruction, etc..
27, Qixia District, Chemical Fiber New Village, Runkang Court, Xianyin North Road No. 9 and other three old neighborhood renovation projects
Start and end date of construction: 2024
Construction content: house roof façade repair and renovation, public facilities renovation and upgrading, sewage pipe network repair, landscape renovation, road improvement, etc.
28. Yuhuatai District Taishan Apartments, Tianhong Villa, Furen Yaju South and other 3 old neighborhoods renovation project
Start and end date of construction: 2024
Construction content: it involves 31 6-story residential buildings and 3 1-story commercial buildings, including new building facade, new landscape works, strong electricity works and weak electricity works.