Three projects in seven days! Lishui major project approval into the "superlane"

Signing the land grant contract on March 21, receiving the construction project planning permit and construction plan review certificate on March 25, receiving the construction project construction permit on March 26, and receiving the real estate right certificate on March 27. ...... This series of approval nodes records the whole process of "achieving all five certificates" in one week after signing the land grant contract of three major projects in Lishui District. Realize the whole process of "five certificates issued together". This year, Lishui District has fully implemented the "five certificates" working mode, so that more projects can "start construction after taking land".

Enterprises: the opening of the project construction "rush" mode  Nanjing Jieya Extrusion Equipment Co., Ltd. is one of the beneficiaries of the "five certificates issued". This high-tech enterprises invested 1.2 billion yuan to build intelligent high-end complete sets of extruder equipment R & D and production projects, after completion will form an annual output of 800 sets (sets) of intelligent equipment production capacity, annual output value is expected to reach 450 million yuan.

After signing the land grant contract on March 21, theIt took the enterprise only five short days to complete the whole process of license application from land acquisition to the commencement of construction."Such a swift approval is beyond our expectation." Liang Qian, assistant general manager of Nanjing Jieya Extrusion Equipment Co.

Also enjoy the "speedy approval" of the expansion project of CNC sheet metal processing equipment production line of Nanjing Haas CNC Machine Tool Manufacturing Co. and the new factory project of Jiangsu Jinhua Intelligent Technology Co. "From the early stage of the project, there are special people to provide us with policy guidance, material preparation, approval and coordination of a full range of services.All the paperwork to start construction was done in a week.." The person in charge of Nanjing Haas CNC Machine Tool Manufacturing Co., Ltd. said that such efficient service effectively reduces the cost of the enterprise and accelerates the project process.

Approval: departmental linkage paves the way for project clearance  The "five certificates" refer to the construction land use planning permit, real estate right certificate, construction project planning permit, construction plan review certificate and construction project construction permit, which are indispensable "passes" for the project to start, involving a number of examination and approval departments, and submitting a lot of materials and cumbersome procedures. It involves many approval departments, and the submission of materials is cumbersome.
  The key to achieving "five certificates issued together" is to optimize the approval process. Lishui District innovatively transforms the original "relay running" tandem approval into "side-by-side running" parallel approval, makes full use of the 40-day golden period from land listing and transaction to public announcement, and starts from the scheme design, construction drawing design, engineering bidding and other matters, and efficiently cooperates with the departments of planning, capital and urban construction to complete the pre-approval in advance, which greatly shortens the approval time. Planning and capital, urban construction and other departments to complete the pre-approval in advance, greatly reducing the length of the approval process.

"The establishment of district and town-level agency service network, by the district + town (street) two-level agency staff full tracking and coordination of the approval of each link, to ensure that each link is seamless, and the approval of related matters 'once through'." Huang Julei, director of the Lishui District Data Bureau Chargé d'affaires Center, introduced thatAfter the implementation of the "five certificates" initiative in Lishui, the project approval has reduced the processing time by nearly 50%In 2024, 23 projects in Lishui District will realize "five certificates are issued", 31 projects will realize "start construction when taking land", and the construction of major projects will press the "acceleration button".

Services: making "five certificates" the norm throughout the region  This year, the Lishui District Data Bureau, in conjunction with the regulation of capital, urban construction and other departments, further deepened the "five certificates issued together" mechanism, and launched the "whole process +" service model, building a whole-area coverage of the agency service network, with the help of data sharing, cross-departmental collaboration, resource integration and other means. By means of data sharing, cross-sectoral collaboration, resource integration, etc.Promoting the comprehensive upgrade of the "five certificates" from "case-by-case breakthroughs" to "regular coverage"The service will be provided wherever there is a demand for it.  Where there is a demand, the approval agency service will follow up to where. At the beginning of the year, the Lishui District Data Bureau agency center of the region's auction projects to conduct a detailed mapping, scheduled the recent 11 new projects to implement the "five certificates issued" mode, by the district-level agency to provide one-on-one accurate reporting counseling. The second quarter at present, there have been seven projects are in full swing to promote.

The "five certificates issued together" initiative is a vivid practice of Lishui District to optimize the business environment and promote the high-quality development of the economy, and is also a key initiative to build a new pattern of "up and down, left and right convergence, and one operation" approval service.Let enterprises realize the leap from "layers of customs clearance" to "one-stop access"..  Dong Qun, deputy director of the Lishui District Data Bureau, said that in addition to the full-process agency services, Lishui District has also continued to improve the mechanism of the district leadership package and task force to promote the implementation of the entrepreneur service day system, strengthened the physical operation of the Business Environment Complaints and Supervision Center, and accelerated the realization of the efficient work chain of "land acquisition is the commencement of the construction, the completion of the project is the commencement of the production, and the pre-inspection is the commissioning".