Heavyweight! 2024 government investment plan out, Lishui 9 big projects bright, involving Ning Xuan Railway

Phase I reconstruction and expansion project of Lishui section of Provincial Road 204

Ningxuan Railway

Qinhuai River (Jiangning Pengfu - Yangtze River Section) Waterway Improvement Project

Qinhuai River and Shishu Lake Water System Connectivity Project

......

Recently, "Nanjing 2024 Government Investment Plan" was officially released, 2024 municipal government investment plan arrangements for the year A class 232 projects, annual planned investment of 51.552 billion yuan; arrangements for B class 102 projects.

The specific arrangements for Category A projects are as follows:

There are 66 projects in comprehensive transportation, with an annual planned investment of 43.94 billion yuan; 103 projects in ecological and environmental protection, with an annual planned investment of 4.012 billion yuan. In terms of livelihood improvement, there are 43 projects with an annual planned investment of 1.924 billion yuan; in terms of social governance, there are 20 projects with an annual planned investment of 1.676 billion yuan.

In terms of construction progress: 128 renewed projects, annual planned investment of 47.705 billion yuan, accounting for about 92.5%; 104 new projects, annual planned investment of 3.847 billion yuan, accounting for about 7.5%.

From the construction sectorThe city construction projects 176, investment of about 48.696 billion yuan, accounting for 94.5%; science, education, culture, health and information technology projects 56, investment of about 2.856 billion yuan, accounting for 5.5%.

I have sorted out 9 important projects involving Lishui, including Phase I of the reconstruction and expansion project of Lishui section of Provincial Highway 204, Ningxuan Railway, waterway improvement project of Qinhuai River (Jiangning Pengfu-Yangtze River section), and Qinhuai River and Shishu Lake water system connection project, etc., which I am going to share with you below.

4 projects in category A:

1、The first phase reconstruction and expansion project of Lishui section of 204 provincial highway

Construction content: a highway taking into account the standard of urban roads, starting from the development zone of Zhetang planning all the way, finally Honglan Hongzhang line, 23.7 kilometers long; set up a tunnel, starting from Binhuai Avenue, and finally traffic West Road.

Years of construction:: 2019-2025.

total investment: $3,582.9 million, with $20,000,000 planned for 2024.

2024 image progress: Completion of the construction of the main structure of the tunnel section, and the main construction of the road section where the conditions for construction are available

On the afternoon of January 30, 2024, the handover and acceptance meeting for the section from Tianshengqiao Avenue to Hongzhang Line of Phase I of the reconstruction and expansion project of Lishui Section of Provincial Highway 204 was held in Lishui District Transportation Bureau and passed the handover and acceptance successfully.

Tianshengqiao Avenue to Hongzhang line section is 5 kilometers long, using highway level one standard construction, design speed of 80 kilometers per hour, divided into the main line of three lanes and non-motorized road, roadbed width of 33 meters.

2、Lishui District Yigan River (Shahekou-Changhe Highway Bridge Section) Treatment Project

Building content:River desilting 3.93 km, embankment reinforcement 0.42 km, embankment seepage control and filling ponds to fix the foundation 0.49 km, the new ecological gabion bank protection 5.18 km, drainage station demolition and construction of 1, culvert demolition and construction of 2, demolition of 1, bridge and culvert construction of a new bridge, the top of the embankment of the new construction and renovation of the flood control road 6.76 km and so on.

Construction start and end years:2023-2024.

Total investment:50.59 million, with $20.59 million planned for 2024.

2024 Image Progress:complete a projectThe

3、Lishui district Qingxi dike remediation project

Building content:Rectification of Qingxi dike, design flood storage capacity of 6.905 million cubic meters, reinforcement of dike length of 8436 meters, the new berm 7317 meters, the new Qingxi dike gate station, the Qingxi River pump gate and connecting culvert gate each one, dike river improvement of 3870 meters.

Construction start and end years:2024-2025.

Total investment:28,000,000, with a planned investment of $48,000,000 in 2024 and a plannedConstruction started in the first quarterThe

2024 Image Progress:50% of work completedThe

4. Public Security Operations Building Project

Building content:It mainly includes the construction project of the Law Enforcement Case Center of the Municipal Public Security Bureau,Lishui Branch Outdoor Training Ground and Target Range Construction Project, Gulou Branch Operational Building Renovation Project, etc.

Construction start and end years:2024-2026.

Total investment:189.71 million, with a planned investment of $73 million in 2024, and a plan toConstruction started in the first quarterThe

2024 Image Progress:Remodeling construction

Five projects in category B:

1、Ningxuan Railway

Building content:The length of the new main line of Ningxuan Railway is 147.11 kilometers, including 115.9 kilometers of Nanjing section and the new Lukou Airport Station,Lishui West StationGaochun Station, the project is designed for a speed of350 km/hThe

Construction start and end years:2024-2028.

Total investment:282,660,000,000 dollars.

According to "Bidding Announcement for Subcontracting of Determining and Drilling for Ningxuan Railway", Ningxuan Railway is located in the south of Suzhou and Anhui province along the river within the urban agglomeration, located in the core area of Nanjing metropolitan area on the axis of north-south development; starting from Nanjing city in Jiangsu province in the north, and then passing through the Jiangning district (Lukou Airport), Lishui district and Gaochun district of Nanjing city in the south, and finally ending up in Xuancheng city, Anhui province, which is located in the south of Suzhou and Anhui province within the urban agglomeration along the river. It is an important part of the second corridor of Ning-Hangzhou and the new rapid railroad corridor of Lu-Su-Anhui-Gan.

The line leads from Nanjing station intercity field, along the Shanghai-Nanjing intercity, Ningwu railroad, Xianning liaison line, Changshen high-speed traffic corridor southbound, Nanjing city reserved Zijinshan East Station, Cangbo Gate Station station conditions; in the Jurong West Station on the north side of the Ninghang Railway, after crossing the west and the proposed Yangzhen-Ningma Railway, set up gates to form a Zhenjiang to Xuancheng direction of the communication path, a total of access to introduce the Lukou Airport in the planning of the lower part of the T3 Terminal Building set Lukou Airport Station; after passing through S1 and S9 lines, it will lead out of the airport and pass through Hengshan to the southeast and then set up Lishui West Station on the south side of Shiqiu in Lishui; after getting out of the station, it will go southward along the Ningxuan Expressway and set up Gaochun Station in Gaochun Gucheng. After leaving the station, it will enter Anhui Province along Ningxuan Expressway and set up Xuancheng Station along Ningxuan Expressway on the east side of Beaver Bridge Town; after leaving the station, it will be introduced into Xuancheng Station along Nanyihu and Shuiyangjiang River.

Ningxuan Railway Nanjing Station to Xuancheng Station, the length of the new line 170.728km, of which the Jiangsu section 127.867km. 31 large and medium-sized bridges, 4 tunnels, the distribution of the entire line of 8 stations, the use of the existing Nanjing Station, Xuancheng Station, reserved Zijinshan East Station, Cangbo Gate Station, the new Lukou Airport, Lishui West, Gaochun and Xuanshou Station.

2、Qinhuai River (Jiangning Pengfu - Yangtze River Section) Waterway Improvement Project

Building content:Improvement of 50.92 kilometers of waterways to Class III standards.8 kilometers of new berms, 1 mooring anchorage, 11 bridges reconstructed, simultaneous construction of signage, landscaping and other projects.

Construction start and end years:2024-2030.

Total investment:287,000,000 dollars.

Qinhuai River waterway is an integral part of the province's "two vertical and five horizontal" trunk waterway network, and it is an important contact line between the Yangtze River golden waterway and the Wushen Line Yangtze River Delta high-grade waterway. The section from Lishui Shishu Lake to Jiangning Pengfu has passed the delivery and acceptance in December 2021, and was officially completed in June 2022 and opened to navigation.

3、Lishui District Tianshengqiao River (Chenjiaqiao - Rouge River Bridge section), Lacqiao River (Dangxixu section) treatment project

Building content:Chenjiaqiao - Rouli River Bridge section: embankment seepage control and reinforcement of 1.78 km, the new top of the embankment road 5.08 km, the waterfront slope bank protection, greening 3 km, the treatment of skimming ditch 3 and along the building renovation, etc.; Dangxi polder section: embankment up to the standard of 3.65 km, seepage control and reinforcement of 1.42 km, the bank slope protection of 5.48 km, the new top of the embankment road 5.18 km, dredging and dredging of 5.1 km and along the supporting buildings renovation of 5 and so on. 5 buildings along the line, etc.

Construction start and end years:2024-2025.

Total investment:$10,000,000.

4Lishui District Ergan River Upstream Section Remediation Project

Building content:Convenience Reservoir spillway to 340 section clearing miscellaneous obstacles, waterward slope masonry, about 250 meters; Wolong Reservoir spillway upstream section of the left bank of the waterward slope masonry and the new embankment top road, about 1.6 kilometers; Kaitai Bridge - Jurong boundary section of the river channel desilting, the right bank of the embankment seepage control treatment and the restoration of the embankment top road, about 1.66 kilometers long.

Construction start and end years:2024-2025.

Total investment:30 million dollars.

5Qinhuai River and Shishu Lake water system connection project

Building content:A new diversion gate and 4.2 kilometers of culverts connecting Tianshengqiao River and Putang River, with a design diversion flow rate of 5 cubic meters per second; improvement of Putang River with a total length of 8.2 kilometers, including siltation and dredging, river protection and the penetration of three dikes; and a new storage project for Xinqiao River, with a water storage level of 5-6 meters.

Construction start and end years:2025-2027.

Total investment:20,000,000 dollars.